Factory-Installed Options G 25
72 wc_tx001085gb.fm
6.12 Containment System
See Graphic: wc_gr002647
Overspills and leaks are captured in the containment system. The
containment system holds over 110% of the fluid contained in the
machine.
The containment system should be checked every 50 hours or 2
weeks and drained when necessary. If fluid is found in the containment
tank, trace the cause of the leak and correct.
Note: In the interests of environmental protection, place impermeable
sheeting and a container under the machine to collect the liquid which
drains off. Dispose of this liquid in accordance with environmental
protection legislation.